GAL Regiunea Rediu - Prăjeni — I7 / L803 – Intervention No. 7 – Renewable Energy
Call for local public authorities in the territory of GAL Rediu-Prăjeni, for investments in renewable energy. Allocation €98,677, 100% support, online submission 13 November–12 December 2026.
- Who can apply
- Only local public authorities (communes) in the GAL territory can apply
- Total budget
- 98,677 euro
- Funding amount
- Maximum 98,677 euro per project
- Submission period
- 13.11.2026 – 12.12.2026, 23:59
Checked against official sources on · funder: GAL Regiunea Rediu - Prăjeni · official source
The guide has not been published yet, but good applications are built before launch. Those who start when the call window opens usually miss out on it.
Who can apply
Only local public authorities (communes) in the GAL territory can apply: Rediu, Valea Lupului, Românești, Movileni, Gropnița, Șipote, Plugari, Vlădeni (Iași) and Prăjeni (Botoșani). Companies cannot apply. The investment must be on the public domain of the UAT, within the GAL territory. Territory of GAL Regiunea Rediu - Prăjeni (only these localities): Rediu, Valea Lupului, Românești, Movileni, Gropnița, Șipote, Plugari, Vlădeni, Prăjeni.
What it covers
- Photovoltaic panels for lighting public buildings
- Photovoltaic panels for public street lighting
- Small-scale hybrid photovoltaic + wind systems for public spaces
- Investments in producing energy from renewable sources in order to reduce energy consumption
- Minimum production capacity of 0.05 MW
Free assessment · 2 minutes
Check whether your company qualifies
Enter your CUI (tax ID): we'll show you instantly whether LAG (Local Action Group, GAL) Regiunea Rediu - Prăjeni — I7 / L803 – Intervention no. 7 – Renewable energy applies in your company's county and field, then a consultant will call you free of charge.
A Todos & Company consultant will contact you within one working day at the details in your subscription.
We prepare your application before the window opens
- We analyse whether you qualify and under which programme exactly.
- We build the application: business plan, budget, supporting documents.
- We submit during the call window and follow the evaluation.
- We stay with you through the reimbursement file and final payment.
Frequently asked questions
Who can submit projects under Intervention 7 at GAL Rediu-Prăjeni?
Only local public authorities (communes) in the GAL territory. The legal representative may be the mayor or their legal substitute.
What is the submission period and where do you submit?
Submission runs from 13.11.2026, 09:00, to 12.12.2026, 23:59, online at www.afir.ro.
How much can you obtain for a project?
Maximum €98,677 per project, with an intensity of 100% of eligible costs. The same amount is the allocation for the entire call window.
Can the energy produced be sold, or can you become a prosumer?
No. Investments in producing energy for sale are ineligible. The energy is for own consumption only, with exclusively off-grid solutions.
What is the minimum selection threshold?
The minimum threshold is 20 points. The maximum score on the grid is 100: installed capacity 30, population served 35, implementation period 35.
How long does it take to prepare the application?
It depends on the complexity of the project and the documents you already have. The first step is the eligibility analysis, which tells you what needs to be prepared.
What happens if I do not qualify?
We tell you before any contract is signed, and if another suitable programme exists, we point you to it.
Funding alerts · free
Not the right programme? Get alerts for your company
Enter your CUI (tax ID): once a month or every two weeks, we will send you the programmes that are open or opening for your company's county and field. Free of charge, and you can unsubscribe at any time.
Emails come from alerte@todos-company.ro; replies go to our consultants.
Next step
We prepare your file before it opens — GAL Regiunea Rediu - Prăjeni — I7 / L803 – Intervention No. 7 – Renewable Energy
Fill in the form and we will tell you whether you qualify. If you do not qualify under this programme, we will tell you which other one you could apply for — or that there is none, if that is the case.
or call us directly on 0755 167 167
Other programmes
e-DRIVE — replacing the fleets of businesses and passenger transport vehicles with zero-emission vehicles
A scheme of 56.9 million euro from the Modernisation Fund. It funds up to 100% of eligible costs for M1, M2 and M3 electric vehicles replacing polluting vehicles. The scheme has been approved (OMTI 742/2026, 817/2026), but the guide and the calls have not yet been published.
Call window openModernisation Fund — stand-alone battery storage installations
The Ministry of Energy is funding new stand-alone batteries with EUR 150 million from the Modernisation Fund, for companies with CAEN code 35. Aid of up to 100%, max. EUR 69,000/MWh and EUR 15 million per company. The submission period in MySMIS2021 was extended on 22 October 2026.
Opening soone-MOVE RO — charging infrastructure for zero-emission mobility
Non-refundable state aid of 262 million euro from the Modernisation Fund for electric charging stations for fleets and the public, with photovoltaics and storage. It is awarded through competitive tenders. The scheme has been approved, but the call has not yet been launched.