PNRR Health: 3,121 contracts completed, 9 hospitals continue under the Health Programme
The deadline for implementing PNRR health projects expired on 15 August 2026 (31 August with an exception). The Ministry of Health reports 3,121 completed contracts and 97% absorption; hospitals that have not finished will continue under the Health Programme.
Todos & Company editorial team · EU funding consultancy since 2006
The implementation deadline for PNRR health investments, extended by the Ministry of Health to 15 August 2026 (with a maximum exceptional extension to 31 August), has now passed. The health component of the PNRR is in its closing phase: the ministry reports 3,121 completed contracts and a 97% absorption rate for non-refundable grants, while hospitals that could not be finished on time have been moved to the 2021–2027 Health Programme. For town halls, county councils and public hospitals, the question has shifted from "how do we finish on time" to "what funding comes next".
In brief
- Programme: PNRR, Health and Digitalisation components (projects managed by the Ministry of Health)
- Authority: Ministry of Health (investment coordinator); MIPE (national PNRR coordination)
- Beneficiaries: public hospitals, local authorities, institutes and healthcare units with PNRR funding contracts
- Implementation deadline: 15 August 2026, by ministerial order published in the Official Gazette, Part I, no. 459/2026; exceptional extension, on request, to 31 August 2026
- Official results (20 October 2026): 3,121 contracts completed; 97% absorption for grants and 100% for the loan component
- Status: deadline expired; PNRR is closing; unfinished hospital projects continue under the 2021–2027 Health Programme
What happened with the 15 August deadline?
On 29 May 2026, the Ministry of Health announced the publication in the Official Gazette of the order of interim minister Cseke Attila setting an extended deadline, 15 August 2026, for completing PNRR-funded investments under the Digitalisation and Health components. Beneficiaries needing extra time could request, under the law, a maximum extension of activities to 31 August 2026. The ministry was then managing approximately 1,200 investment projects in hospitals, medical equipment and digital systems.
The date of 31 August 2026 was not a national choice but the European limit of the mechanism: MIPE had announced since the start of 2026 that the implementation of reforms and investments funded through the PNRR must be completed by 31 August 2026, and on 14 September it specified that final results are quantified after submission of payment request no. 6, the last in the programme. Coordinators of reforms and investments, including the Ministry of Health, were required to report their data by 15 September 2026.
What does the Ministry of Health's balance sheet show?
The ministry communicated the closing progress step by step. On 28 August 2026 it announced a 91% absorption rate of PNRR EU funds, up from 66%, and asked beneficiaries to upload supporting documents quickly on the dedicated platforms for reimbursement. On 4 September it reported payments of over 1 billion lei made in August, and, in the period 31 August – 4 September alone, payments of 340,058,551.79 lei to hospitals and institutes across the country.
The statement by the interim minister of 20 October 2026, at the handover of office, contains the most complete results published so far:
- 3,121 PNRR contracts completed;
- 97% absorption for non-refundable grants and 100% for the loan component;
- 7 hospitals completed;
- 188 hospitals digitalised;
- 2,536 medical practices renovated or equipped;
- 78 integrated community centres built, renovated or equipped;
- 115 public hospitals equipped with equipment for reducing hospital-acquired infections;
- 35 intensive care units with investments in neonatal infrastructure.
Among the works accepted in the final days of the programme is the Regional Centre for Vascular-Cerebral Pathology and Neurosurgery in Cluj, announced as completed and accepted on 29 August 2026, an investment of over 50 million euro, with 105 beds and 6 operating theatres.
What happens to the hospitals that were not finished?
Hospital projects that did not fit within the PNRR timetable were transferred to the 2021–2027 Health Programme. On 23 October 2026, the Ministry of Health announced the signing of the orders to start works for the Timișoara Regional Oncology Institute (1.7 billion lei, 250 beds, 65,000 sq m) and for the new building of the Giurgiu County Emergency Hospital (258.5 million lei, 122 beds), both funded through the Health Programme after the transfer from the PNRR. Minister Alexandru Rogobete stated that none of the nine transferred projects will be abandoned and that the transfer meant saving the investments, not giving them up.
For beneficiaries with projects unfinished on 31 August, MIPE has not yet published a general rule on how to handle them: funded activities had to be completed by the deadline, with the exceptions provided by legislation, and the situation of each contract is clarified with the investment coordinator. The final list of completed projects will be published by MIPE in the PNRR Dashboard after submission of payment request no. 6.
What this means for your institution or company
The recommendations below are the consultant's, not official obligations.
- If you are a PNRR health beneficiary: check now that all reimbursement requests, acceptance reports and supporting documents have been uploaded and accepted. The ministry explicitly requested this in August, and the final results are set after payment request no. 6 is submitted.
- If you have a project transferred from the PNRR: funding continues through the Health Programme, but under the rules of that programme (new contract, indicators, deadlines). Ask the managing authority in writing for the updated timetable and conditions.
- If you are a local authority (UAT) or hospital without a PNRR project: the next sources for healthcare infrastructure are the Health Programme calls and the regional programmes. One open example is the call for family doctors' practices in the four ITIs. You can quickly run the eligibility check to see which calls suit you.
- If you are a supplier of medical equipment or IT: the PNRR market has closed; demand is shifting towards Health Programme contracts and towards state budget investments in the transferred hospitals.
A common trap: treating the "extension" as an opportunity to apply. The 15 August deadline concerned only the implementation of contracts already signed; there was no new call for proposals at this stage.
Frequently asked questions
Can I still submit a PNRR health project?
No. The PNRR implementation period ended on 31 August 2026, and the 15 August deadline concerned exclusively the completion of previously contracted investments. New funding for healthcare infrastructure comes through the 2021–2027 Health Programme and through the regional programmes.
What exactly did the order of 29 May 2026 provide?
An extended deadline, 15 August 2026, for completing PNRR investments under the Digitalisation and Health components, plus the possibility for beneficiaries to request, under the law, a maximum extension to 31 August 2026. The order was published in the Official Gazette, Part I, no. 459/2026; the order number does not appear in the ministry's press release.
How many new hospitals were completed under the PNRR?
According to the interim minister's statement of 20 October 2026, 7 hospitals were completed under the PNRR. Nine hospital projects were transferred to the Health Programme, including the Timișoara Regional Oncology Institute and the new building of the Giurgiu County Hospital, for which the orders to start works were signed on 23 October 2026.
When will the final PNRR results be known?
MIPE announced on 14 September 2026 that the final results on completed projects will be quantified after submission of payment request no. 6, the last in the programme, and will be published in the PNRR Dashboard on the ministry's website. Romania's total allocation after the August 2026 renegotiation is 20.11 billion euro, of which 13.57 billion is grants and 6.54 billion is loans.
Does a beneficiary with works unfinished on 31 August lose the money?
No official reimbursement mechanism has been announced under the PNRR for the part not executed and not accepted by the deadline. For hospital projects, the ministry chose the transfer to the Health Programme; for other investments, continuation depends on own resources or the state budget. The situation of each contract must be clarified directly with the Ministry of Health.
Official sources
- Ministry of Health, 29 May 2026: implementation deadline for PNRR Health projects extended to 15 August 2026
- Ministry of Health, 28 August 2026: 91% absorption rate of PNRR EU funds
- Ministry of Health, 29 August 2026: Regional Centre for Vascular-Cerebral Pathology and Neurosurgery Cluj, completed and accepted
- Ministry of Health, 4 September 2026: payments of over 1 billion lei through the PNRR in August 2026
- Ministry of Health, 20 October 2026: statement by interim minister Cseke Attila (PNRR results)
- Ministry of Health, 23 October 2026: Hospital construction continues (IRO Timișoara and SJU Giurgiu, through the Health Programme)
- MIPE, 14 September 2026: information on completed PNRR projects will be available after payment request no. 6 is submitted