Net-zero technologies: authorisation in 9–18 months and a single digital point of contact (PCUEL)
EU Regulation 2024/1735 limits the permitting of "net-zero" technology factories to 12–18 months, and of strategic projects to 9–12 months. In Romania, PCUEL, approved by the Government on 28 August 2026, is the single point of contact.
Todos & Company editorial team · EU funding consultancy since 2006
Companies that want to build or expand net-zero technology factories in Romania (solar panels, batteries, heat pumps, electrolysers, grid components and more) benefit, under Regulation (EU) 2024/1735, from maximum authorisation deadlines: 12 months for an annual capacity below 1 GW and 18 months above that threshold. Projects recognised as "strategic" are authorised even faster, in 9–12 months. On 28 August 2026, the Government approved the regulation of the Single Electronic Contact Point for industrial licences (PCUEL), the platform through which these projects will deal with a single authority. Please note: the regulation does not provide money, it shortens and simplifies authorisation.
In brief
- Legal act: Regulation (EU) 2024/1735 on the European ecosystem for the manufacturing of net-zero technologies (Net-Zero Industry Act), published in the OJ L on 28 June 2024
- Authority in Romania: the Industrial Licence Office (OLI), which takes over and operates the PCUEL platform
- Beneficiaries: promoters of net-zero technology manufacturing projects (companies of any size), with particular attention to SMEs
- Authorisation deadlines: 12 months (below 1 GW), 18 months (1 GW or more), 18 months for capacities not measured in GW
- Strategic projects: 9 months (below 1 GW), 12 months (1 GW or more, or capacity not measured in GW)
- Status: the EU regulation applies; the Government Decision (HG) on the PCUEL regulation was adopted on 28 August 2026, with phased implementation
What has changed compared with what was known in December 2025?
At the end of 2025 there was talk of an "OLI platform" that would give net-zero investments priority in funding. The official documents show something different. On 28 August 2026, at an extraordinary Government meeting, the Decision approving the Regulation on the administration and use of the Single Electronic Contact Point for industrial licences was adopted. According to the Government's press release, PCUEL will bring together, in a single digital procedure, the opinions, agreements, authorisations and licence required for industrial activities. The applicant will have a single access point and will register only once, without being asked for the same documents several times.
Also according to the press release, PCUEL will act as the single point of contact for projects concerning critical raw materials, net-zero technologies and renewable energy production. Once the reform is implemented, the single industrial licence will be obtained within a maximum of 180 days from the valid submission of the application. The Decision responds to PNRR milestone 246 (Component 9, Investment 1) and is linked to milestone 243, on the reform of industrial activity authorisation. Implementation is phased, and the date from which the platform will actually take over the function for net-zero projects as well has not been made public.
Which technologies fall under the regulation?
Article 4 of Regulation (EU) 2024/1735 lists the net-zero technologies. They include:
- solar technologies (photovoltaic, solar thermal electric, solar thermal) and wind technologies;
- batteries and energy storage;
- heat pumps and geothermal energy;
- hydrogen, including electrolysers and fuel cells;
- sustainable biogas and biomethane;
- CO2 capture and storage, plus CO2 transport and use;
- electricity grids, including charging stations for transport;
- energy efficiency linked to the energy system, including district heating networks;
- sustainable alternative fuels, hydropower, nuclear and transformative industrial technologies for decarbonisation.
The regulation covers the manufacture of these technologies and their components, not the installation of a photovoltaic park for self-consumption. The EU's target is that by 2030 European manufacturing capacity will cover at least 40% of annual deployment needs.
How does authorisation through the single point of contact work?
Article 6 requires Member States to have a single point of contact that coordinates the entire authorisation procedure. It is the project promoter's only interlocutor. Documents can be submitted electronically, and the authorities cannot ask again for studies or permits already issued for the same project. The steps set out in Article 9:
- Within 45 days at most of receiving the application, the single point of contact confirms that the file is complete or requests additional information. The authorisation period starts running from the confirmation.
- Within two months at most of receiving the application, a detailed timetable for the procedure is published.
- Authorisation does not exceed 12 months (below 1 GW) or 18 months (1 GW or more). The environmental impact assessment stages are not included in this period.
- In exceptional cases, the period may be extended once, by 3 months at most, and the reasons are communicated in writing.
How does a project obtain "net-zero strategic project" status?
The application for recognition is submitted to the Member State and must contain evidence of the criteria in Article 13, a business plan showing financial viability and an indicative project timetable. The criteria include adding manufacturing capacity for a technology on which the EU depends for more than 50% on imports, or contributing to the competitiveness of SMEs in the supply chain. The Member State assesses the complete application within one month. If the application is rejected, the applicant can turn to the Commission, which assesses it within 20 working days.
Article 13(4) is particularly relevant for Romania. Projects located in less developed and transition regions and in territories supported by the Just Transition Fund, eligible for cohesion funds, are recognised as strategic after the award procedure is completed, on the basis of a simple written request. The same applies to projects receiving money from the Innovation Fund or through the European Hydrogen Bank auctions.
Strategic projects receive the highest status of national importance available, are considered to be of overriding public interest in environmental procedures, and disputes relating to them are treated as urgent, where national law provides for urgent procedures. Authorisation takes 9 months below 1 GW and 12 months above that threshold. On request, the European net-zero platform provides advice on project financing, but recognition does not automatically mean a grant.
What this means for your business
Our recommendation: if you are planning a production line for battery components, inverters, panel structures, heat pumps or grid equipment, prepare your file now as for a strategic project. You need a solid business plan, a realistic timetable and evidence of import dependence in your segment. Strategic status shortens authorisation and carries weight with funders. In practice, funding comes from other sources: state aid schemes, the Innovation Fund, the STEP instruments or PDDTJ.
Common pitfalls:
- Confusing strategic project status with funding. The regulation does not provide money.
- Assuming that PCUEL already handles all procedures. Implementation is phased, so check with OLI (contact@oli.gov.ro) which functions are active on the date you submit.
- Underestimating the environmental assessment, which is not included in the 9–18 month deadlines.
If you want to know which non-refundable funding suits your investment, start with the eligibility check.
Frequently asked questions
Will I receive money if my project becomes a "net-zero strategic project"?
Not directly. Regulation (EU) 2024/1735 grants priority in authorisation, maximum deadlines of 9–12 months and advice on financing. The money comes from separate programmes, such as state aid schemes, the Innovation Fund or cohesion funds.
What is the single point of contact in Romania?
According to the Government press release of 28 August 2026, the Single Electronic Contact Point for industrial licences (PCUEL), operated by the Industrial Licence Office, will also be the single point of contact for net-zero technology projects. Implementation is phased.
Does a photovoltaic park for self-consumption fall under these rules?
The regulation concerns projects for the manufacture of net-zero technologies and their components. Installing renewable capacity has its own authorisation rules, but PCUEL will also be the single point of contact for renewable energy projects.
How long does it take to authorise a net-zero technology factory?
A maximum of 12 months for an annual capacity below 1 GW and 18 months for 1 GW or more, or for capacities not measured in GW. The period runs from the confirmation of the complete file and may be extended once, by 3 months at most.
Official sources
- Regulation (EU) 2024/1735 (Net-Zero Industry Act) – EUR-Lex
- Text of Regulation (EU) 2024/1735 published in the OJ L, 28 June 2024 (PDF)
- European Commission – Net-Zero Industry Act
- Romanian Government – acts adopted at the extraordinary meeting of 28 August 2026 (GD on the PCUEL regulation)
Information checked on 27 September 2026. Conditions may be amended by the managing authority — check the guide in force before submitting.