Anghel Saligny: almost 1.1 billion lei for arrears, from budget reallocations
On 30 October 2026, the Government announced that it had found almost 1.1 billion lei for the Anghel Saligny arrears, out of a total of 2.3 billion lei. The difference will follow through the budget revision in November. Details on the amounts set aside have not been officially published.
Todos & Company editorial team · EU funding consultancy since 2006
On 30 October 2026, the Government announced that it had found solutions for paying almost 1.1 billion lei in arrears under the "Anghel Saligny" National Investment Programme. The details of how the sums reserved for beneficiaries with 20% co-financing will be redistributed were not published in any official source that we could verify.
In brief
- Programme: the "Anghel Saligny" National Investment Programme (local infrastructure: water, sewerage, roads, bridges, gas).
- Authority: the Ministry of Development, Public Works and Administration.
- Beneficiaries: administrative-territorial units (town halls, county councils). Companies take part as contractors carrying out the works.
- Arrears: almost 1.1 billion lei to be paid immediately, out of total arrears of 2.3 billion lei; the difference is to follow through the November budget revision.
- Deadlines for the reserved sums: not officially announced in any source we have verified.
- Status: the Government announced measures to reallocate funds on 30 October 2026; we have not verified whether any legislative act has been published in the Official Gazette.
What happened to the programme in 2026?
OUG 87/2025 made 2026 transfers conditional on the local or county budget covering 20% of the amount corresponding to the state budget contribution, with no subsequent reimbursement. Beneficiaries had 30 calendar days from the entry into force of the budget law to communicate their estimated sums, together with the decision of the local or county council; those who did not submit lost their right to transfers in 2026. The same ordinance required the Government to approve, by decision, prioritisation criteria based on the categories of investment and the rate of drawdown under the funding contracts.
According to public statements, on 10 September 2026 the Ministry of Development announced that the 2026 funds had been exhausted, and from 11 September the submission of new transfer requests through the digital platform was suspended. Authorities that had committed to 20% co-financing had their sums reserved. We did not open the ministry's press release on its official page, so treat this information as reported by the press.
What did the Government decide on 30 October?
In the briefing at the end of the meeting, the Government said that almost 1.1 billion lei will go towards Anghel Saligny arrears, and that over 680 million of this comes from a reallocation of funds within the Ministry of Development's budget. Total arrears stand at 2.3 billion lei, and the difference is to be covered through the November budget revision.
The exact details (whether and how the reserved sums are reduced, the deadlines for applying, the method of payment) do not appear in the official sources we found and must be checked in the text of the legislative act once it is published.
What this means for your business
Recommendation:
- If you are a builder or supplier on an Anghel Saligny contract: ask the beneficiary for the status of the transfer requests submitted and the sums reserved. Payment will probably come partly, in instalments, rather than in full.
- If you are a town hall or county council with 20% co-financing: submit your requests for the reserved sums as soon as possible and check the deadlines in the published legislative act. Sums not requested could be redistributed.
- Planning: do not commit to new works relying on unconfirmed transfers. For new projects, look for alternative sources: regional programmes, PNRR or AFIR.
You can check which funding is open for your locality or company with the eligibility check.
Frequently asked questions
Can new transfer requests still be submitted under Anghel Saligny?
According to the statements made in September 2026, the submission of new requests through the digital platform was suspended once the funds were exhausted. Resumption depends on the budget being topped up. We have not found an official date for resumption.
How much of the arrears is being paid now?
The Government announced that it has found almost 1.1 billion lei out of 2.3 billion lei in arrears. The rest is to follow through the November budget revision, the amount of which has not yet been announced.
What happens to the sums reserved for the 20% co-financing?
According to the September statements, beneficiaries who had committed to 20% co-financing had their sums reserved. We have not found an official source on any reduction of these sums or on a deadline for applying.
Do the prioritisation criteria still apply?
OUG 87/2025 provides for prioritisation criteria approved by the Government. We have not found an official source saying that they no longer apply to payments of arrears.
Official sources
- Government of Romania – briefing after the meeting of 30 October 2026
- OUG 87/2025 – Legislative Portal
- EU Opportunities – "Anghel Saligny" National Investment Programme
Information checked on 2 November 2026. The conditions may be amended by the managing authority — check the guide in force before submitting.